Home > NRC Library > Document Collections > General Communications > Information Notices > 1993 > IN 93-08
UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, D.C. 20555 February 1, 1993 NRC INFORMATION NOTICE 93-08: FAILURE OF RESIDUAL HEAT REMOVAL PUMP BEARINGS DUE TO HIGH THRUST LOADING Addressees All holders of operating licenses or construction permits for nuclear power reactors. Purpose The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to alert addressees to the failure of certain residual heat removal (RHR) pump bearings due to high thrust loading. It is expected that recipients will review the information for applicability to their facilities and consider actions, as appropriate, to avoid similar problems. However, suggestions contained in this information notice are not NRC requirements; therefore, no specific action or written response is required. Background On November 10, 1987, reactor operators at the Seabrook Station noted that the "A" RHR pump had become noticeably noisier. The RHR pumps at Seabrook are of an Ingersoll-Rand model 8X20WDF driven by a Westinghouse vertical, 400-horsepower motor (frame 5009P39). After operators measured the vibration, they declared the pump inoperable and removed it from service. Operators disassembled the pump and found that the thrust bearing had been damaged. Subsequent analysis of the failed bearing concluded that the bearing had been subject to a thrust loading substantially greater than the design value of 7,562 newtons (1,700 pounds force). In situ testing was performed to determine the actual thrust on both the A and B train RHR pumps. The measured values confirmed that the bearing thrust loading was significantly greater than the design value and varied with flow rate. A licensee event report, LER 50-443/88-09, was submitted which described the failure and the proposed corrective actions. The corrective actions were to include modification of the Seabrook RHR pumps and further testing of a spare pump at the vendor facility. During the period between July 20 and August 2, 1992, an NRC inspection team conducted a probabilistic risk assessment based inspection at the Seabrook Station. The potential failure of the RHR pump due to high thrust bearing load was identified as a result of this inspection. This prompted further licensee review and a supplemental LER was issued in November 1992, describing actions taken to address the problem. 9301260132. IN 93-08 February 1, 1993 Page 2 of 3 Description of Circumstances On November 19, 1992, North Atlantic Energy Service Corporation, the licensee for Seabrook Station, filed an LER supplement (LER 50-443/88-09 R1) documenting actions taken following the 1987 failure of an RHR pump thrust bearing. The supplement states that the modification consisted of reducing both the inner diameter of the suction side wear ring and the outer diameter of the impeller wear area. The bearing design was not modified. The supplement notes that thrust bearing loading, although reduced by the modification, would remain substantially above the original design value, reducing the expected life of the bearing. The LER supplement also documented the results of the testing of the spare pump at the vendor facility. The test results verified that the in situ values were not caused by such site-specific factors as installation details or piping geometry. Thus, the test results indicated that all pumps of the same design were probably subject to similar high thrust values. NRC Inspection Report No. 50-443/92-80 contains additional information about this matter. Discussion The licensee estimated that the operating time for the failed Seabrook RHR pump corresponded to about eight refueling outages, due to extended operation of the RHR system preceding issuance of the full-power license. Other facilities that have the same model pumps could be vulnerable to the same failure mechanism. The RHR pump thrust test results are shown in Figure 1, adapted from a licensee report. The highest thrust values occurred in the flow range of 3,785 - 9,842 liters per minute (1,000 - 2,600 gallons per minute) and remained well above the design thrust in that range even after the pumps were modified. During normal shutdown cooling operation, RHR flow typically exceeds 11,356 liters per minute (3,000 gallons per minute) which is sufficient flow to remain above the design thrust of the bearings, but during mid-loop conditions, the flow rate is limited to a maximum of 5,678 liters per minute (1,500 gallons per minute). Such a reduction is necessary to prevent the formation of a vortex and the consequent introduction of air into the RHR pump suction that could cause cavitation and damage the pump (see NRC Generic Letter 88-17, "Loss of Decay Heat Removal.") The Figure 1 thrust values for the mid-loop flow rate were about three times the original design value before the Seabrook pumps were modified. The thrust values for mid-loop operation remain at about 175 percent of design value after the modification. The design life of the bearing was substantially reduced because of the higher thrust conditions. Seabrook has developed maintenance schedules to ensure thrust bearings are replaced before they reach the end of predicted service life. . IN 93-08 February 1, 1993 Page 3 of 3 This information notice requires no specific action or written response. If you have any questions about the information in this notice, please contact one of the technical contacts listed below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager. ORIGINAL SIGNED BY Brian K. Grimes, Director Division of Operating Reactors Support Office of Nuclear Reactor Regulation Technical contacts: James E. Beall, RI (215) 337-5374 Patricia L. Campbell, NRR (301) 504-1311 Attachments: 1. Figure 1. Ingersoll-Rand Test Curve - RHR Pump Thrust Bearing Loads 2. List of Recently Issued NRC Information Notices .
Page Last Reviewed/Updated Wednesday, February 16, 2011