Defense Infrastructure: Challenges Increase Risks for Providing Timely Infrastructure Support for Army Installations Expecting Substantial Personnel Growth

GAO-07-1007 Published: Sep 13, 2007. Publicly Released: Sep 13, 2007.
Jump To:
Skip to Highlights

Highlights

The Army expects significant personnel growth, more than 50 percent in some cases, at 18 domestic bases through 2011 because of the effect of implementing base realignment and closure (BRAC), overseas force rebasing, and force modularity actions. This growth creates the need for additional support infrastructure at these bases and in nearby communities. Military construction costs of over $17 billion are expected for new personnel, and communities will incur infrastructure costs as well. GAO prepared this report under the Comptroller General's authority to conduct evaluations on his own initiative. It addresses (1) the challenges and associated risks the Army faces in providing for timely infrastructure support at its gaining installations and (2) how communities are planning and funding for infrastructure to support incoming personnel and their families. GAO analyzed personnel restationing numbers, discussed planning efforts with Army and community officials, and visited nine of the larger gaining bases and nearby communities.

The Army has developed plans to accommodate the growth of about 154,000 personnel at its domestic bases, but it faces several complex implementation challenges that risk late provision of needed infrastructure to adequately support incoming personnel. First, Army plans continue to evolve, and Army headquarters and each of the nine gaining bases we visited were relying on different numbers of personnel movements and were not fully aware of the causes for the variances. For example, Fort Benning officials expected more than 6,000 additional soldiers and military students than Army headquarters planned. Because consistency in the relocation numbers is important for properly determining not only base infrastructure support needs but those of nearby communities as well, inconsistent numbers could lead to an improperly sized facilities' infrastructure. Second, the Army faces challenges in synchronizing personnel movements with planned newly constructed on-base infrastructure improvements. Any significant delays in implementing planned actions could place the Army at risk of not meeting BRAC statutory deadlines. Third, competing priorities could lead the Army to redirect resources planned for needed infrastructure improvements and operations to such priorities as current operations in Iraq and Afghanistan, as has happened in the past. However, such redirection of resources could undermine the Army's ability to complete infrastructure improvements in time to support personnel movements and to meet planned timelines. Fourth, the Army Corps of Engineers, the primary construction agent for the Army, must manage an unprecedented volume of construction, implement a new construction strategy designed to save construction costs and time, and complete infrastructure improvements within available resources and planned timelines. The Army recognizes these challenges and is refining its implementation plans to overcome these challenges. While communities surrounding growth bases GAO visited have generally proactively planned for anticipated growth, they have been hindered in fully identifying additional infrastructure requirements and associated costs by the evolving nature of the Army's plans and different interpretations of the plans. For example, while Army officials at Fort Benning, Georgia, project an influx of about 10,000 school-age children, the Department of Defense's (DOD) November 2006 figures project only about 600. At the time of our review, these disparities remained unresolved. Communities surrounding growth bases have their own unique infrastructure improvement needs, such as schools, housing, or transportation, based on (1) the number of personnel to actually move to the nearby base, (2) the community's current capacity in its area(s) of need, and (3) the community's own capacity to finance additional infrastructure requirements and the availability of federal or state assistance to finance these needs. Some communities had already sought federal and state assistance to help finance construction efforts at the time of GAO's review even though the evolving nature of the Army's planning prevented the communities from having reasonable assurance that they knew the full scope of their infrastructure requirements.

Recommendations

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense To better facilitate infrastructure planning, the Secretary of Defense should direct the Secretary of the Army to determine why there are differences between headquarters and gaining bases with respect to the number of arriving and departing personnel.
Closed – Implemented
In a series of reports GAO issued to discuss emerging issues associated with the implementation of the BRAC 2005 round, overseas rebasing, and force modularity initiatives, GAO reported on the challenges and risks the Army faces in providing adequate infrastructure when needed at its major gaining bases. GAO reported that one challenge to planning for the movement of troops was that the numbers being used by Headquarters were different than the gaining bases. To better facilitate infrastructure planning, we recommended that the Secretary of Defense direct the Secretary of the Army to determine why there were differences between headquarters and gaining bases with respect to the number of arriving and departing personnel. In responding to our report the Army wrote that it had determined the cause of the differences between the numbers and had taken corrective action. In January 2007 the Army designated the Army Stationing and Installation Plan (ASIP) as the single, unified source of installation planning population data to be used Army wide. Furthermore, in May 2008, the Army issued guidance that helped reduce the differences between the populations reported by Headquarters and the installations by ensuring that ASIP population data be used for reporting external to the Army and allowing pre-decisional unit moves to be used for internal planning. Lastly, the Army established an ASIP quarterly edit cycle to resolve discrepancies between Army official force structure data and the "on the ground" situation. According to the ASIP Program Manager at the time of the review, there will always be differences between the data in ASIP and what is available at the installation level because installations get pre-decisional information that is not yet in ASIP because the actual moves have not yet been approved by the Army's Vice chief of Staff, but the quarterly ASIP edit cycle is in place to resolve discrepancies and all discrepancies are vetted with HQDA G3/517 for review. This reconciliation process has resolved the problems that were apparent before. Once the discrepancies are discussed the ASIP and Force structure documents are updated to reflect any necessary changes. In a subsequent GAO report issued in June 2010, we reported that Installation officials told us that the quarterly updates to the ASIP system had been a great improvement and had enhanced their facility planning to have more current Installation population data available.
Department of Defense To better facilitate infrastructure planning, the Secretary of Defense should direct the Secretary of the Army to ensure that Army headquarters and base officials are collaborating to agree on Army personnel movement plans so that base commanders and surrounding communities can effectively plan for expected growth. This collaboration to reach agreement should continue as expected personnel movement actions are revised over time.
Closed – Implemented
In a series of reports GAO issued to discuss emerging issues associated with the implementation of the BRAC 2005 round, overseas rebasing, and force modularity initiatives, GAO reported on the challenges and risks the Army faces in providing adequate infrastructure when needed at its major gaining bases. GAO reported that one challenge to planning for the movement of troops was that the numbers being used by Headquarters were different than the gaining bases. To better facilitate infrastructure planning, we recommended that the Secretary of Defense direct the Secretary of the Army to ensure that the Army Headquarters and base officials are collaborating to agree on Army personnel movement plans so that base commanders and surrounding communities can effectively plan for expected growth. In responding to our report the Army wrote that it had taken corrective action. In May 2007 the Army issued guidance that allowed installations to plan for anticipated moves that may not be reflected in the Army Stationing and Installation Plan (ASIP) and to discuss these plans with local communities as long as they are appropriately qualified as pre-decisional and subject to change. In addition, the Army established an ASIP quarterly edit cycle to resolve discrepancies between Army official force structure data and the "on the ground" situation. Furthermore, The Army issued a memorandum of Agreement between the office of the Assistant Chief of Staff for Installation management and the Office of the Deputy chief of Staff G-3/5/7 to close information gaps and improve timely reconciliation of disparate data between installation planners, force planners, and headquarters. According to the ASIP Program Manager at the time of the review, there will always be differences between the data in ASIP and what is available at the installation level because installations get pre-decisional information that is not yet in ASIP because the actual moves have not yet been approved by the Army's Vice chief of Staff, but the quarterly ASIP edit cycle is in place to resolve discrepancies and all discrepancies are vetted with HQDA G3/517 for review. This reconciliation process has resolved the problems that were apparent before. Once the discrepancies are discussed the ASIP and Force structure documents are updated to reflect any necessary changes. In a subsequent GAO report issued in June 2010, we reported that Installation officials told us that the quarterly updates to the ASIP system had been a great improvement and had enhanced their facility planning to have more current Installation population data available.

Full Report

Office of Public Affairs

Topics

Army basesArmy personnelBase realignmentsConstruction costsCost analysisDefense economic analysisMilitary basesMilitary facilitiesMilitary facility constructionSchedule slippagesStrategic planningCost growthProgram implementation